STANTON SPORT AVIATION

STANTON AIRFIELD

STANTON,  MINNESOTA USA

 

Where the heck is STANTON??

 

 

NEW! -Construction at Stanton July 2005

 

 

 

Ensign Hangars

 

CONSTRUCTION VIEWS – Stanton, Minnesota

 

These images are from Stanton Airfield, Stanton Minnesota.  Two Ensign “Northern Edition” Sailplane hangars are being built here.

 

To the right is a picture of one of the prepared sites.  We first had an excavator remove 2 feet of topsoil with heavy equipment.  We then had 24-inches of crushed aggregate placed in the “hole,” with the top of the fill compacted and leveled to become the new “grade-level” referred to on the blueprints supplied by Ensign’s Engineering firm.  Though only 6 inches of fill is called out on the plans, we wanted to use plenty of dry, well-drained fill to minimize the effect of frost heave on the slab.  The site was slightly over-sized to allow some improved drainage as well.

 

CLICK PHOTOS TO ENLARGE

 

The NORTHERN EDITION plans calls for 18-inch wide and 48-inch deep footings for the three support posts.  This then required the concrete to be reinforced with a 12-inch wide, 40-inch deep rebar cage for each footing.  We spent about $65 per building for the #3 (3/8th inch) and #4 (1/2-inch) rebar called out in the plans.

 

The box contains rebar ties (wire loops) needed for making the rebar cages.

Pat Watson and Kent Johnson used a torch to first cut the rebar to the sizes needed.  The stock material came in 10-foot lengths.  We cut the #3 material in thirds (40”) and the #4 material in half.  For one building’s worth this took nine #3 and five #4 10-foot lengths respectively for the three cages.

We used chalk to mark the cuts and within 30 minutes it was all cut.   Set-up and cutting took roughly 1-man hour per building.

We then used the torch and a 1-foot pipe to make the 180-degree bends in the #4 material (heating up the bend point), and used a hole in a tractor hitch to aid manually bending the #3 material into a circle (no heat used).  This part took 2-man hours.

Pat Watson and Tom Rent showing off the last of the cages.  Building 6 cages took 4-man hours (only 3 cages were needed for each building). 

The final set of cages

 

 

ON TO THE NEXT PAGE - the BIG DIG!

 

 

 

Back to Prior Page