STANTON SPORT AVIATION

STANTON AIRFIELD

STANTON,  MINNESOTA USA

 

Where the heck is STANTON??

 

 

NEW! -Construction at Stanton July 2005

 

 

 

Ensign Hangars

 

CONSTRUCTION VIEWS – Stanton, Minnesota

CLICK PHOTOS TO ENLARGE

 

 

The building sites were staked out with the 5 key stakes (rear, tips, front-center, and front-dish).  If is important to locate these points accurately.

The rear and tip stakes were then surrounded by 4 witness pins at 6 foot from the key stake.  This is important in being able to find the original stake-point once the hole is dug.

A template was used to allow a center starter hole to be dug prior to using the Dingo machine.  This helped assure the Dingo bit began its work at the right point.  We removed the template before using the Dingo as the Dingo would likely catch on it and bust it apart.

A Toro Dingo machine with a 18-inch wide bit and a 48” deep reach was used to drill the holes.  This took 2 working hours with 3 people.  Dingo cost was $114 for 3 hours.  The Dingo bit would drift a bit and it took some care to get the hole vertical and wide enough.

The Dingo saved a lot of back-breaking work in removing dirt from these holes..

A hole with witness lines strung to check that the center is still good.

Witness lines show true center of hole.

Tube tested for center.

Tube backfilled and leveled.  The lathe on the right was used to set proper elevation using a level.  Our 2 sites were not at the same grade but we wanted each to be level. Raised tubes will require more local fill before the slab is poured.

Another tube backfilled and leveled.  Note this tube was at grade.

Final step!  Rebar cage added, centered, and connecting rebar shown to tie the footing to the slab.

 

 

 

 

 

 

 

 

ON TO THE FOOTING POUR!

 

Back to Prior Page

 

Back to First ENSIGN Page